Steps for migration
  1. Upgrade BE to 7.1.2. Then, using the hardware replacement guide for UCM and Unity Connection, build a new UCM publisher and Unity Cxn both w/ the IP address of the current server. Then do a disaster backup of UCM and Unity and restore them to their respective servers. Do this will be on a separate network of course.
  2. Change the IP addresses of Unity Cxn and UCM Publisher for their new segment.
  3. Install the servers in their new location and swing DHCP to the new cluster.
  4. Wait for a few days for the system to stabilize. Re-install the current UCMBE server as subscriber 1 in the new cluster and shift the phones accordingly.

Please note that you will not be able to restore data back onto the CM and CX server separately. When you run DRS on the CUCMBE, it will spit out files which will be used by both CM and CX.

You can reuse the 7828 server for the Unified CM. It will support 1000 phones.

Please click here for more information on UCM
Please click here for more information on Unity Cxn Hardware Replacement Guides.
Please click here for more information on Cisco MCS 7825-I4
Please click here for more information on Cisco MCS 7828-I4 Unified Communications Manager Business Edition Appliance

Citation - This blog post does not reflect original content from the author. Rather it summarizes content that are relevant to the topic from different sources in the web. The sources might include any online discussion boards, forums, websites and others.

1 comment :

  1. Does this mean that you cannot restore the DRS files to the new CM pub and CUC pub?

    ReplyDelete

 
/* Google Analytics begin ----------------------------------------------- */ /* Google Analytics end ----------------------------------------------- */